Page 1 - VIADRUS CLEO

VIADRUS CLEO WALL BOILER OPERATION AND INSTALLATION MANUAL

Page 2

10 Fig.No.2 VIADRUS CLEO K boiler assembly 4.2. Control elements Boiler control front panel The thermometer measures the outlet water to

Page 3 - VIADRUS CLEO X

11 1. Burner control unit – ignition and ionisation (ACCF) Electronic device for flame operation and control, for a direct burner ignition by means

Page 4

12 - emergency thermostat connection - regime selection in operation and the reset by means of rotating position switch positioned on the board. -

Page 5 - 3. Technical data

13 CHARAKTERISTIKA TŘÍRYCHLOSTNÍHO ČERPADLA NYL 53-15r1r2r3012345600,511,522,533,544,5PRŮTOK (m3/h)VÝTLAČNÁ VÝŠKA (m)r1r2r3 Legend: NYL 53-15 Three-s

Page 6 - 4. Boiler description

14 BERTELLI automatics function If there is a short-circuited space thermostat, the pump keeps running ( though the boiler is switched off). The

Page 7

15 Current regulation range for a slow ignition 0 – 80% I max Current regulation range of max heating output 0 – 100% I max Electric parameters

Page 8

16 Fig. No. 4 Amplifier sensitiveness measuring circuit Table of values ( 230V~ 50 Hz) Start ON operation ON operation OFF Ionisation current

Page 9

17 P1 – heating position switch P3 –HSW temperature setting P5 – starting output JP1 – fuel setting JP4 – floor heating setting P2 –CH temp

Page 10 - 4.2. Control elements

18 Legend: (down from top): HSW flow sensor/HSW thermal probe/SH thermal probe/modulator/pressure switch/manostat/space thermostat/network supply-phas

Page 11

19 No.. 6 VIADRUS CLEO K wiring diagram Legend: (down from top): HSW flow sensor/HSW thermal probe/ /modulator/pressure switch/flue gases thermostat/

Page 12

2 Dear customer We thank you that you have bought the VIADRUS CLEO boiler thus having shown your confidence in ŽDB a.s.Bohumín, VIADRUS

Page 13

20 5. Positioning and installation 5.1. Regulations and guidelines a) regarding the heating system ČSN 060310 : 1998 Central heating and asse

Page 14

21 5.2 Installation conditions Only a firm authorized for boilers installation is allowed to install VIADRUS CLEO gas boiler on the basis of the des

Page 15 - RT = RTO x e

22 Fig. No. 7 Boiler main dimensions 5.3. Positioning The boiler positioning must correspond to the project documentation. The boiler is posit

Page 16

Boiler positioning with regard to the fire regulations: A safe distance from the combustible materials − When installing and operating the boil

Page 17

Fig. No. 8 Boiler console for suspension on the wall. Fig. No. 9 Boiler connection Legend: HSW inlet/ HSW outlet/ gas inlet/ CH outlet/ CH

Page 18

6. Commissioning 6.1 Connection to the system 6.1.1.Connection to the heating system and filling with water VIADRUS CLEO boiler is design

Page 19

Before the gas pipes connection to the boiler the gas pipes must be tested and revised. All gas joints after their connection to the boiler must

Page 20 -

6.2. Boiler commissioning The whole installation must correspond to the relevant regulations for this equipment. The boiler must be com

Page 21 - 5.2 Installation conditions

Legend: Modulation regulator cover / Modulation regulator/ Gas pressure on the nozzle measurement/ gas inlet pressure measurement/ modulation reg

Page 22 - 5.3. Positioning

is obliged to acquaint the user with the boiler operation. The user by his signature in the guarantee certificate confirms that he was acquainte

Page 23

3 TABLE OF CONTENTS 1. Manufactured boiler variants...

Page 24

Behaviour in case of a failure: In case of a flame simulation the ignition is prevented. Note: If GMF unit at the flame control detects the fla

Page 25 - 6. Commissioning

 The boiler is fully automatic and is isn’t recommended to disconnect it from electricity  The boiler is equipped with automatic protection ag

Page 26

10. Guarantee and liability for defects Závod topenářské techniky VIADRUS provides: – The boiler guarantee for 24 months after the date the prod

Page 27 - 6.2. Boiler commissioning

Intended for user ŽDB a.s.ZTTVIADRUS Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boiler Boiler

Page 28 - 7. Boiler operation by user

Intended for service organization ŽDB a.s.ZTTVIADRUS Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boil

Page 29 - 8. Maintenance

Intended for manufacturer ŽDB a.s.ZTTVIADRUS Guarantee certificate and Quality and completeness certificate for VIADRUS CLEO… boiler Boi

Page 30

Annex to the guarantee certificate for customer- the user Record of accomplished guarantee and after-guarantee repairs and regular product

Page 33 - VIADRUS CLEO… boiler

4 2. Boiler usage and advantages VIADRUS CLEO wall boiler with a flow-heater is designated for combustion of low-pressure natural gas. Th

Page 34

5 3. Technical data operating temperature and electric values VIADRUS CLEO K VIADRUS CLEO T Type of fuel [-] ZP ZP Appliance category

Page 35

6 Tab. č. 2 Thermal – technical parameters Reference conditions 15°C a 1013,25 mbar, dry gas Output for CH [kW] 8 – 24 Output for HSW [kW] 8

Page 36

7 pump. On the internal heating water outlet there is installed an emergency thermostat , a pressure switch and a clack-valve of the manometer for si

Page 37

8 Fig.No.1 VIADRUS CLEO T boiler assembly Legend(down from top): HSW temperature sensor/ air manostat/ bleeder valve/exhaust ventilator/ Expansi

Page 38

9 ignition electrode/ burner/supporting frame/ pressure switch/ circulation pump/ Honeywell gas valve/ safety valve/refill valve/ HSW flow sensor Le